Genco Logistics, Atlanta

Genco Logistics, Atlanta, GA came to SRT Group with a problem; they had 1,500,000 lbs of pallet rack (and that’s a lot of racking!) they had to get out of a warehouse after a lost lease. Genco had several other contractors come in and gave them shy-high prices to take down and dispose of all the scrap before they came to SRT Group.  By that time, the contract only had 30 days before the new tenant was due to move in. SRT had the right equipment and men on site within 48 hours. A crew of 26 men took 26 days to dismantle and remove all the racking and the new tenant moved in on time.  Best of all, SRT found a buyer for the scrap and the total cost to Genco was $0.00.